As executive director of the Grand Parkway Association, David Gornet has been advocating for the construction of the 180-mile loop for 16 years. He became executive director for the association in 2001. Prior to that he worked as a planning and construction consultant. Before his work with the GPA, Gornet worked for 18 years as director of transportation and planning with a consulting firm in Houston. He holds bachelor’s and master’s degrees in civil engineering and is a registered professional engineer in Texas. Gornet said the best thing about being involved in the Grand Parkway construction is the ability to lessen travel time for drivers so they can spend more time with their families.
How long did it take Grand Parkway to get started locally in Harris and Montgomery counties?
Environmental studies were started in 1999, and designs were approved in 2009 for Harris County and in 2010 for Montgomery County. In 2012 the design was passed to [the Texas Department of Transportation] in both counties, and construction began in 2013.
What is the estimated cost and end date for construction on the Grand Parkway?
The estimated cost of construction is $1.2 billion, plus the cost of the land. We’re estimating a finishing date sometime in the latter part of 2015.