University Boulevard North extension and rail relocation[/caption]
1. University Boulevard North extension and rail relocation
University Boulevard North in Sugar Land is being extended approximately 1,000 feet from Union Pacific Railroad to connect to Stadium Drive. Starting in mid-May, the city of Sugar Land began work on Hwy. 90 related to the project. A portion of the median was removed from west of the proposed University Boulevard North intersection with Hwy. 90 to just west of Ulrich Street, according to the city. The existing intersection will be altered, including removal of the signal and removal of the left-turn movement during construction. Phase 1 of the project is due for completion in late summer with Union Pacific Railroad’s work set for around October 2016. Phase 2 of the project will be funded and led by Johnson Development and is expected to be completed by 2018.
Timeline: August 2015-summer 2016 (Phase 1) Cost: $16.15 million (Phase 1-2) Funding sources: city of Sugar Land, Fort Bend County, Sugar Land tax increment reinvestment zone district
2. Festival Site roadway project
As part of Sugar Land’s 2013 Parks Bond Program, the city is building a 52-acre festival site adjacent to the Brazos River and Hwy. 59. The roadway at the festival site is under construction. The grading and drainage work is being constructed, and work on a deceleration lane from the Hwy. 59 frontage road will follow. Installations of an irrigation system and turf, as well as extending power to the site, are ongoing. The project also includes a four-lane divided concrete roadway, parking and trail access, sidewalks and other features.
Timeline: February 2015-2018 Cost: $2.6 million Funding sources: city of Sugar Land, Tax Increment Reinvestment Zone No. 3