Curious as to what new businesses and renovations are underway or coming to Sugar Land and Missouri City? The following projects have been filed in the last two weeks through the Texas Department of Licensing and Regulation. The following information may be subject to change.
1. Ridgeview Park: 3902 Ridgeview Drive, Missouri City
Type of work: renovation/alteration
Timeline: Jan. 17-April 1
Estimated cost: $870,000
2. Armstrong Elementary: 3440 Independence Blvd., Missouri City
Type of work: renovation/alteration
Timeline: Jan. 31-April 30
Estimated cost: $54,000
3. Talyard Brewing Co.: 1033 Imperial Blvd., Sugar Land
Type of work: new construction
Timeline: March 1, 2022-March 1, 2023
Estimated cost: $9 million
4. Shanell's Playhouse: 18722 University Blvd., Ste. 100, Sugar Land
Type of work: renovation/alteration
Timeline: Jan. 14-March 31
Estimated cost: $150,000
5. Houston Methodist Sugar Land Hospital: 16655 Southwest Freeway, Sugar Land
Type of work: new construction
Timeline: May 2, 2022-Feb. 28, 2025
Estimated cost: $206 million