As part of the Northeast Expansion project, the Texas Department of Transportation announced a series of road closures from Dec. 29-Jan. 4.

What you need to know

Several roadways and exits will be closed for roadway work. Drivers should use alternative routes due to congestion caused by construction.

I-35 from FM 3009 to FM 1518
  • The right lane on southbound I-35 frontage road will be closed from FM 3009 to Schertz Parkway until Jan. 25 for roadway work.
I-35 from FM 1518 to Loop 1604
  • The left lane on northbound I-35 frontage road will be closed from Forum Parkway to Forum Access Road until Aug. 2 for construction work.
  • The northbound I-35 exit ramp to Evans Road will be closed until May 5 for construction work.
  • The northbound I-35 frontage road and exit ramp from Forum Parkway to Olympia Parkway will be closed from 9 p.m.-5 a.m. Jan. 3-4 for cap work.
  • The left lane on southbound I-35 frontage road from Forum Parkway to Old Austin Road will be closed until May 25 for bridge and roadway work.
  • There will be a full closure of the westbound I-35 collector ramp and northbound I-35 to westbound Loop 1604 connector ramp from 9 p.m.-5 a.m. Jan. 2-5 for deck and overhangs column work.
  • There will be a full closure of the southbound I-35 to westbound Loop 1604 connector ramp from 9 p.m.-5 a.m. Jan. 2-5 for deck and overhangs column work.
  • There will be a full closure of the eastbound frontage road from entrance ramp to IKEA-RBFCU Parkway and a full closure of northbound and southbound lanes of IKEA-RBFCU Parkway at Loop 1604 from 9 p.m.-5 a.m. Jan. 2-5 for deck and overhangs column work.
  • There will be an exit ramp closure at Olympia Parkway from 9 p.m.-5 a.m. Jan. 2-5 for deck and overhangs column work.
Loop 1604 from I-35 interchange to Nacogdoches Road
  • The left lane on eastbound frontage road of Loop 1604 from Lookout Road to IKEA-RBFCU Boulevard will be closed until March 31 for construction.
  • The left lane of westbound Loop 1604 frontage work and the exit ramp from Gateway Boulevard to Lookout Road will be closed from 9 p.m.-5 a.m. Jan. 3-4.
  • There will be a full closure of westbound Loop 1604 frontage road and the exit ramp from Gateway Boulevard to Gateway Place, and the southbound I-35 connector ramp to westbound Loop 1604 mainlanes from 9 p.m.-5 a.m. Jan. 3-4 for bridge beam setting
I-35 from Walzem Road to Eisenhauer Road
  • There will be a full exit ramp closure on northbound I-35 mainlanes from Walzem Road from 11 p.m.-7 a.m. Jan. 3 for drilled shaft work.
  • Two lanes will be closed on northbound I-35 frontage road from Eisenhauer Road to Galahad Drive from 11 p.m.-7 a.m. Jan. 3 for drilled shaft work.
  • The right lane of northbound I-35 from 11 p.m.-7 a.m. Jan. 3 for bridge work.
  • The exit ramp on northbound I-35 to Walzem Road will be closed from 9 p.m.-8 a.m. Jan. 4 for drilled shaft work.
  • Multiple lanes of northbound I-35 will be closed from Eisenhauer Road to Galahad Drive from 9 p.m.-8 a.m. Jan. 4 for drilled shaft work.
  • The right lane of northbound I-35 from Eisenhauer Road to Galahad Drive will be closed from 9 p.m.-8 a.m. Jan. 4 for bridge work.
I-35 from Rittiman Road to I-410 South interchange
  • Multiple right-hand lanes on southbound I-35 from Rittiman Road to Petroleum Drive will be closed from 9 p.m.-5 a.m. Jan. 2-3 for drilled shaft work.
  • Multiple right-hand lanes on southbound I-35 from Rittiman Road to Petroleum Drive will be closed from 9 p.m.-8 a.m. Jan. 4 for drilled shaft work.
For more information, visit I-35 NEX project's website.