Wondering what renovations and new construction are underway or set to begin soon in Round Rock and Pflugerville? The following commercial projects have been filed through the Texas Department of Licensing and Regulation. All information, including cost and timeline, is subject to change.
1. Emerson Automation Solutions courtyard infill: 1100 W Louis Henna Blvd. W., Round Rock
Type of work: additions to existing building
Timeline: Jan. 2-Sept. 29
Estimated cost: $2.3 million
Scope of work: new building addition (infill) between two existing buildings; 50% of the project is an amenity building area, and 50% is the exterior courtyard
2. Cody Pools: 101 E Old Settlers Blvd., Round Rock
Type of work: renovation/alteration
Timeline: Dec. 9-March 3
Estimated cost: $675,000
Scope of work: demolition and finish-out of an existing demised tenant suite
3. Grand Avenue Plaza: 114 Grand Avenue Parkway, Pflugerville
Type of work: new construction
Timeline: March 1-May 1, 2023
Estimated cost: $1.5 million
Scope of work: new construction of two retail buildings' shell
4. Target: 121 Louis Henna Blvd., Round Rock
Type of work: renovation/alteration
Timeline: April 25-Aug. 22
Estimated cost: $2.53 million
Scope of work: modify office layout and convert office space into stock at front of store for order pickup efforts; add optical to office space; convert food service to Starbucks; modify guest service, fitting rooms, and restrooms; replace check lanes; update finishes
5. Atmos Energy office renovation: 3110 N. I-35 Frontage Road, Round Rock
Type of work: renovation/alteration
Timeline: Jan. 3-Sept. 30
Estimated cost: $1.4 million
Scope of work: office renovation of existing office building gutting the interior with new finish-out, adding new exterior windows and openings, new break room, covered patio, new mechanical system, modified plumbing and electrical systems to support new finish-out