Wondering what renovations and new construction are underway or set to begin soon in Round Rock and Hutto? The following commercial projects have been filed through the Texas Department of Licensing and Regulation. All information, including cost and timeline, is subject to change.
Dell Round Rock 5 Computer Room air handler replacement—200 Dell Way, Round Rock
Type of work: renovation/alteration
Timeline: Jan. 31, 2021-Sept. 1, 2022
Estimated cost: $180,000
Scope of work: HVAC unit replacement
Titan Hutto VI—Limmer Loop and Innovation Boulevard, Hutto
Type of work: new construction
Timeline: Feb. 1-May 11
Estimated cost: $500,000
Scope of work: project involves design and construction of a new, one-story, 196,128-square-foot tilt-up concrete building located in Hutto; the building will contain speculative space serving warehouse functions for future tenants
119 Louis Henna Commercial—119 Louis Henna Blvd., Round Rock
Type of work: new construction
Timeline: May 2, 2022-May 25, 2023
Estimated cost: $1 million
Scope of Work: new 8,000-square-foot retail building
Infinitum Electric—106 E. Old Settlers Blvd., Ste. D-106, Round Rock
Type of work: renovation/alteration
Timeline: Jan. 3-March 4
Estimated cost: $350,000
Scope of work: interior remodel of an existing space in an existing building
St. David’s Round Rock CT scan renovation—2400 Round Rock Ave., Round Rock
Type of work: renovation/alteration
Timeline: Jan. 3-April 4
Estimated cost: $250,000
Scope of work: renovation of existing CT scan room to new layout for new CT scan machine