Check out six ongoing transportation project updates across the Austin metro that could impact your commute.
Blakey Lane extension
Project: The road will be extended from Edward Burleson Lane south to an intersection with roundabout options at Old Austin Highway in Bastrop.
Update: Construction began May 25, according to city records.
- Timeline: 2026-29
- Cost: $7 million-$8 million
- Funding sources: transportation impact fees; roadway maintenance funds; water and wastewater fees
Chisholm Trail South improvements
Project: The city is reconstructing Chisholm Trail Road from Sam Bass Road to RM 620 in Round Rock, with drainage, pedestrian and lighting improvements.
Update: The discovery of utility lines within the project have delayed its completion from summer 2026 to fall, per city officials.
- Timeline: roadway completion expected mid-fall 2026
- Cost: $4.26 million for construction
- Funding source: type B sales tax revenue
New Hope Drive expansion
Project: Traffic changes are underway as the city of Cedar Park expands New Hope Drive from four to six lanes and introduces an innovative intersection at 183A Toll.
Update: Construction is active between Block House Drive and CR 180, with a traffic shift involving the left-turn lanes from 183A onto New Hope Drive. Design work continues on the western segment toward Lakeline Boulevard, per city officials.
- Timeline: 2024-27
- Cost: $1.8 million (design)
- Funding source: 2022 transportation bond
Oak Hill Parkway
Project: The 7-mile stretch of highway has been undergoing a $677 million facelift since 2021. The Texas Department of Transportation is currently reconstructing Hwy. 290 in Oak Hill, transforming the existing four-lane, undivided roadway to a six-lane divided highway with new frontage roads and 14 miles of shared-use paths, according to TxDOT documents.