Upcoming projects
Kenney Fort Boulevard extension segments 5 and 6
Project: The project will extend Kenney Fort Boulevard to University Boulevard from its current terminus at East Old Settlers Boulevard in Round Rock.
Update: Round Rock City Council approved the purchase of 1.5 acres of land using eminent domain in November. The project is currently under design.
Timeline: construction timeline not yet available
Cost: $493,841 (land purchases), full cost not yet available
Funding source: Type B sales tax revenue
SH 130 frontage road connections
Project: The project will build northbound and southbound frontage roads for SH 130 from north of Limmer Loop to south of CR 118 in Hutto.
Update: Design for the project was largely completed in late summer.
Ongoing projects
Burnet Road Mobility Program
Project: The project will feature updated traffic signals, improved crossings, bus stop improvements, trail connections, curb extensions, drainage improvements, shared-use paths, raised medians and more on Burnet Road in Austin, from White Horse Trail to US 183, Bright Verde Way to MoPac, and US 183 to Bright Verde Way.
Update: Construction crews continue working on roadway, drainage, utility and shared-use path improvements along Burnet Road. Shared-use path and roadway preparation is nearing completion.
FM 685 at Kelly Lane intersection improvements
Project: The project consists of creating dedicated left-turn and U-turn lanes as well as signal modifications in Pflugerville. Once completed, both frontage roads will have two straight lanes, two left-turn lanes with one acting as a turnaround lane combination and one right-turn lane.
Update: Pflugerville City Council approved the construction contract with Joe Bland Construction on Aug. 11. Construction on the project began on Oct. 26.
I-35 Capital Express South Project
Project: The Texas Department of Transportation will add two high-occupancy-vehicle lanes, a southbound bypass lane and pedestrian and bicycle paths to I-35 in Austin.
Update: Intermittent nightly closures of the flyovers from eastbound and westbound Hwy. 71 to southbound I-35 will continue through the end of the year.
Timeline: 2022-28 (total project)
Cost: $548 million
Funding sources: Capital Area Metropolitan Planning Organization, TxDOT
Completed projects
Ronald Reagan Boulevard lane widening
Project: The project widened approximately 7 miles from FM 3405 to Hwy. 29 in Liberty Hill, including separated northbound and southbound roadways. The old road now carries northbound traffic. Part of the construction effort included turn lanes and shoulders.
Update: Williamson County officials hosted a ribbon-cutting ceremony Nov. 19 to celebrate the completion of construction.