The Texas Department of Transportation is reconstructing and improving the Oltorf Street interchange at I-35 from south of Woodland Avenue to Woodward Street. Crews are continuing installation of drainage infrastructure, construction of new curbs and driveways, and pavement preparation and installation along the northbound frontage road. The contractor has completed the majority of construction on the new Oltorf Street bridge and has shifted and reopened all lanes. Work continues on construction of retaining walls along the main lanes of I-35.

Timeline: February 2017-spring 2019


Cost: $42.6 million


Funding source: TxDOT’s congestion relief initiative Texas Clear Lanes