Transportation update: FM 423 Construction of the Frisco portion of FM 423 will be complete in July.[/caption]

Construction of the Frisco portion of FM 423 will be complete in July. The roadway is being widened from four to six lanes from US 380 to Eldorado Parkway.

Construction on FM 423 from Stewarts Creek Road to SH 121 is also being widened. This section is nearly complete with an estimated completion date in the fall.

Timeline: October 2014-July 2017 (US 380 to Eldorado Parkway), October 2014-October 2017 (Stewarts Creek Road to SH 121)

Cost: $29.8 million (US 380 to Eldorado Parkway), $900,000 (Stewarts Creek Road to SH 121)

Funding source: TxDOT