Hardin Boulevard, McKinney Ranch Parkway widening
Paving and striping along Hardin Boulevard is expected to be complete sometime in August, and the newly constructed roadway is expected to be open to the public by the end of August. Meanwhile, traffic on McKinney Ranch Parkway between Hardin and US 75 will be detoured as crews construct the southern portion of the road.
When complete, Hardin will be widened from four lanes to six lanes between SH 121 and McKinney Ranch, and McKinney Ranch will be widened from two lanes to four lanes between Hardin and US 75.
Timeline: April-December Cost: $3.7 million Funding source: city of McKinney
Virginia Parkway widening
Paving operations for the median widening will continue along Virginia Parkway from Ridge Road to Bellegrove Drive. Lane closures are expected, and at least one lane will remain open in each direction at all times.