FM 1488 widening west of Magnolia
Project: Between the Waller County line and FM 1774, FM 1488 is being widened from two to four lanes with a continuous left turn lane.
Update: This project is 99% completed, according to a March 10 media update from the Texas Department of Transportation.
- Timeline: November 2020-third quarter 2025
- Cost: $35.35 million
- Funding source: state funds
Project: FM 1488 is being widened from two to four lanes with a continuous left turn lane between FM 1774 and west of FM 149.
Update: According to a March 10 media update from TxDOT, this project is 58% completed.
- Timeline: June 2022-second quarter 2027
- Cost: $48.3 million
- Funding source: state funds
Project: Between FM 1488 and I-45, TxDOT is using existing right of way on Hwy. 242 to widen lanes and restripe the intersections.
Update: This project is 50% completed, according to a March 10 media update from TxDOT.
- Timeline: October 2023-fourth quarter of 2026
- Cost: $29.11 million
- Funding sources: federal, state funds