1. FM 1488 widening
Project: TxDOT is widening FM 1488 to four lanes with a continuous left-turn lane from FM 1774 to west of FM 149 in Magnolia.
Update: The project was 30% complete as of a Sept. 1 update, the latest available from TxDOT.
- Timeline: June 2022-first quarter 2025
- Cost: $48.28 million
- Funding source: TxDOT
Project: A TxDOT project is underway to widen FM 1488 to four lanes with a continuous left-turn lane between the Waller County line and FM 1774 in Magnolia.
Update: The project was 68% complete as of Sept. 1. The cost of construction increased from $30.33 million in August.
- Timeline: November 2020-second quarter 2024
- Cost: $35.3 million
- Funding source: TxDOT
Project: A TxDOT project has begun in Magnolia to add a raised median on FM 1488 between Mostyn Drive and I-45.
Update: After months of delays, the project was 9% complete as of Sept. 1 and under construction by contractor ISI Contracting Inc.
- Timeline: summer 2023-fourth quarter 2025
- Cost: $10.22 million
- Funding sources: TxDOT, state