1. Houston Methodist Magnolia Emergency Care Clinic: 18230 FM 1488, Magnolia
Type of work: renovation/alteration
Timeline: Nov. 1, 2022-March 31, 2023
Estimated cost: $1.17 million
Square footage: 11,202
Scope: interior renovation of an existing emergency care clinic
2. ABC-123 Early Learning Center: 26643 Nichols Sawmill Road, Magnolia
Type of work: new construction
Timeline: Dec. 1, 2022-June 1, 2023
Estimated cost: $1.3 million
Square footage: 11,000
Scope: new construction of a single-story building
3. Shipley Do-Nuts: 13774 Jordan Lewis Way, Bldg. H, Ste. 100, Magnolia
Type of work: renovation/alteration
Timeline: Oct. 12, 2022-Jan. 12, 2023
Estimated cost: $225,000
Square footage: 1,779
Scope: interior build-out of a grab-and-go doughnut shop
4. Texas Neuro-Rehab Center: 32605 Tamina Road, Magnolia
Type of work: new construction
Timeline: Aug. 1, 2022-Jan. 1, 2023
Estimated cost: $1.1 million
Square footage: 9,200
Scope: proposed office building
5. Sauced Up: 36825 FM 1774, Magnolia
Type of work: new construction
Timeline: Oct. 3, 2022-Feb. 6, 2023
Estimated cost: $140,000
Square footage: 4,036
Scope: restaurant and bar build-out
6. Marco's Pizza: 13774 Jordan Lewis Way, Ste. 300, Magnolia
Type of work: new construction
Timeline: Sept. 30-Dec. 31
Estimated cost: $80,000
Square footage: 1,187
Scope: build-out of a restaurant
7. The Gathering Church: 1047 E. Huffsmith Road, Tomball
Type of work: renovation/alteration
Timeline: Nov. 14, 2022-Jan. 13, 2023
Estimated cost: $145,000
Square footage: 4,800
Scope: remodel an existing warehouse into a church; add additional parking
8. Le Sugar Salon: 213 Houston St., Tomball
Type of work: new construction
Timeline: Jan. 1, 2023-June 1, 2023
Estimated cost: $350,000
Square footage: 1,879
Scope: new construction of a hair salon
9. G Motors: 23518 Coons Road, Tomball
Type of work: new construction
Timeline: Dec. 1, 2022-Oct. 31, 2023
Estimated cost: $3.75 million
Square footage: 17,678
Scope: new dealership and showroom
10. Wired Electric Services: 13910 Alice Road, Tomball
Type of work: new construction
Timeline: Nov. 1, 2022-Jan. 31, 2023
Estimated cost: $2.1 million
Square footage: 26,000
Scope: new construction of a warehouse and corporate office