Tree and shrub clearing has begun along Robinson Road in Oak Ridge North in the beginning stages of the
Robinson Road widening project. The clearing is being performed by Elite Construction and Engineering Services at a cost of $83,294 to the city. Occasional lane closures will be announced while the clearing project is ongoing.
Crews will be working on the clearing Sept. 24 from Patsy Lane to South Harlan Lane. No lanes are scheduled to be closed, but drivers are encouraged to be aware of flaggers and lane shifts.
Timeline: September-TBD
Cost: $83,294
Funding source: Oak Ridge North