Several township-funded projects are coming to The Woodlands in 2025, with several already underway and others scheduled to start in the new year.

1. The Woodlands Fire Station No. 5

Project: The Woodlands Township is constructing a new fire station to replace the original Fire Station No. 5 following a number of issues surrounding the old building's condition as part of a $14.5 million package for fire department improvements, according to previous Community Impact reporting. The station is set to have 23,000 square feet of space, which will house the fire department and members of the Montgomery County Hospital District.

Update: A groundbreaking ceremony was held on Aug. 22 for the fire station, and construction is underway.
  • Location: 8001 McBeth Way, The Woodlands
  • Timeline: August 2024-December 2025
  • Funding source: The Woodlands Township
2. The Woodlands Emergency Training Center

Project: The Woodlands Township will also fund a number of improvements to the Emergency Training Center as part of the $14.5 million project to rebuild Fire Station No. 5. The improvements include additional shower and bathroom space, expanding the clean burn space and additional structural improvements.
  • Location: 16135 I-45 S., Conroe
  • Timeline: August 2024-December 2025
  • Funding source: The Woodlands Township
3. Alden Bridge Sports Park


Project: The Woodlands Township will begin phase one of a $17.8 million project to remodel the Alden Bridge Sports Park, which will include the conversion of a small grass field to the park's “championship field” with all-weather turf, bleachers and scoreboard. The improvements will also including 224 additional parking spaces, several new grass fields and a restroom facility.

Update: The township will work with the Texas Department of Transportation to install an additional traffic light on Hwy. 242, and it has already received approval for permitting, officials said.
  • Location: 4751 Hwy. 242, The Woodlands
  • Timeline: July 2025-March 2026
  • Funding source: The Woodlands Township
4. 50th anniversary statue

Project: A "First Fifty" anniversary sculpture has been proposed to be placed in the roadway median at the intersection of Woodlands Parkway and Grogans Mill Road to pay homage to all eight villages in The Woodlands.

Update: Architecture firm LANDology Inc., will oversee the design and construction of the sculpture as of Oct. 23, and $1.2 million is budgeted for the project
  • Location: median at the intersection of Woodlands Parkway and Grogans Mill Road
  • Timeline: January 2025-mid 2025
  • Funding source: The Woodlands Township
5. Water Fountain at Waterway Square


Project: The Woodlands Township board of directors identified a renovation of the water fountain at Waterway Square as a key budget priority for 2025 during August budget workshops, allocating an estimated $6.4 million for a remodel of the fountain.

Update: The township board will evaluate the design and construction of the fountain at a future board meeting.
  • Location: 31 Waterway Square Place, The Woodlands
  • Timeline: 2025
  • Funding source: The Woodlands Township