1. Fred Astaire Dance Studio: 16069 City Walk Drive, Sugar Land
Type of work: renovation/alteration
Timeline: Feb. 24-March 31
Estimated cost: $114,500
2. Dickey's Barbecue Pit: 15823 Southwest Freeway, Ste. B22, Sugar Land
Type of work: renovation/alteration
Timeline: March 1-June 1
Estimated cost: $350,000
3. Bath & Body Works: 5760 Hwy. 6, Ste. 3, Missouri City
Type of work: renovation/alteration
Timeline: May 2-July 8
Estimated cost: $200,000
4. Kelsey Seybold Medical and Diagnostic Center: 11555 University Blvd., Sugar Land
Type of work: new construction
Timeline: July 1, 2022-Nov. 1, 2023
Estimated cost: $49 million
5. Niagara Bottling: 14810 Fairway Pines Drive, Missouri City
Type of work: renovation/alteration
Timeline: March 11-Sept. 9
Estimated cost: $510,000