Curious as to what new businesses and renovations are underway or coming to Sugar Land and Missouri City? The following projects have been filed in the last two weeks through the Texas Department of Licensing and Regulation. The following information may be subject to change.

1. Kelsey Seybold Medical and Diagnostic Center: 11555 University Blvd., Sugar Land

Type of work: new construction

Timeline: July 1, 2022-Nov. 1, 2023

Estimated cost: $49 million


2. Niagara Bottling: 14810 Fairway Pines Drive, Missouri City

Type of work: renovation/alteration

Timeline: March 11-Sept. 9

Estimated cost: $510,000


3. Rouxpour: 2298 Texas Drive, Sugar Land

Type of work: renovation/alteration

Timeline: March 21-Aug. 26

Estimated cost: $800,000


4. Island Xpress Car Wash: 5350 Sienna Parkway, Missouri City

Type of work: new construction

Timeline: April 1-Dec. 31

Estimated cost: $1.5 million


5. German Doner Kebab: 2148 Texas Drive, Sugar Land

Type of work: renovation/alteration

Timeline: April 1-Oct. 1

Estimated cost: $750,000