1. Kelsey Seybold Medical and Diagnostic Center: 11555 University Blvd., Sugar Land
Type of work: new construction
Timeline: July 1, 2022-Nov. 1, 2023
Estimated cost: $49 million
2. Niagara Bottling: 14810 Fairway Pines Drive, Missouri City
Type of work: renovation/alteration
Timeline: March 11-Sept. 9
Estimated cost: $510,000
3. Rouxpour: 2298 Texas Drive, Sugar Land
Type of work: renovation/alteration
Timeline: March 21-Aug. 26
Estimated cost: $800,000
4. Island Xpress Car Wash: 5350 Sienna Parkway, Missouri City
Type of work: new construction
Timeline: April 1-Dec. 31
Estimated cost: $1.5 million
5. German Doner Kebab: 2148 Texas Drive, Sugar Land
Type of work: renovation/alteration
Timeline: April 1-Oct. 1
Estimated cost: $750,000