Curious as to what new businesses and renovations are underway or coming to Sugar Land and Missouri City? The following projects have been filed in the last two weeks through the Texas Department of Licensing and Regulation. The following information may be subject to change.

1. Ridgeview Park: 3902 Ridgeview Drive, Missouri City

Type of work: renovation/alteration

Timeline: Jan. 17-April 1

Estimated cost: $870,000


2. Armstrong Elementary: 3440 Independence Blvd., Missouri City

Type of work: renovation/alteration

Timeline: Jan. 31-April 30

Estimated cost: $54,000


3. Talyard Brewing Co.: 1033 Imperial Blvd., Sugar Land

Type of work: new construction

Timeline: March 1, 2022-March 1, 2023

Estimated cost: $9 million


4. Shanell's Playhouse: 18722 University Blvd., Ste. 100, Sugar Land

Type of work: renovation/alteration

Timeline: Jan. 14-March 31

Estimated cost: $150,000


5. Houston Methodist Sugar Land Hospital: 16655 Southwest Freeway, Sugar Land

Type of work: new construction

Timeline: May 2, 2022-Feb. 28, 2025

Estimated cost: $206 million