1. Ridgeview Park: 3902 Ridgeview Drive, Missouri City
Type of work: renovation/alteration
Timeline: Jan. 17-April 1
Estimated cost: $870,000
2. Armstrong Elementary: 3440 Independence Blvd., Missouri City
Type of work: renovation/alteration
Timeline: Jan. 31-April 30
Estimated cost: $54,000
3. Talyard Brewing Co.: 1033 Imperial Blvd., Sugar Land
Type of work: new construction
Timeline: March 1, 2022-March 1, 2023
Estimated cost: $9 million
4. Shanell's Playhouse: 18722 University Blvd., Ste. 100, Sugar Land
Type of work: renovation/alteration
Timeline: Jan. 14-March 31
Estimated cost: $150,000
5. Houston Methodist Sugar Land Hospital: 16655 Southwest Freeway, Sugar Land
Type of work: new construction
Timeline: May 2, 2022-Feb. 28, 2025
Estimated cost: $206 million