1. Ocusoft Pharmacy: 3701 Hwy. 6, Sugar Land
Type of work: renovation/alteration
Timeline: Nov. 11-Oct. 11
Estimated cost: $150,000
2. Lovesac: 16535 Hwy. 59, Ste. 2001, Sugar Land
Type of work: renovation/alteration
Timeline: Jan. 10-March 11
Estimated cost: $110,000
3. Waters Edge Winery of Missouri City: 9018 Sienna Crossing Drive, Ste. 100, Missouri City
Type of work: new construction
Timeline: Nov. 1-March 31
Estimated cost: $170,000
4. Prime Urgent Care: 19900 Hwy. 59, Sugar Land
Type of work: new construction
Timeline: Nov. 12-Feb. 12
Estimated cost: $178,241
5. Benefits Communications Group: 4630 Riverstone Blvd., Missouri City
Type of work: renovation/alteration
Timeline: Nov. 1-Jan. 31
Estimated cost: $307,000