Construction is underway on Champion Drive to upgrade the road from a two-lane asphalt roadway to a two-lane concrete paved section between FM 1960 and Cypress Creek. The project is on track for completion this spring, said Pamela Rocchi, director of Harris County Precinct 4’s Capital Improvement Projects Division.
Timeline: Sept. 24, 2018-April 5, 2020
Cost: $13.2 million
Funding sources: Harris County Precinct 4, Champions Municipal Utility District