The Texas Department of Transportation will bid two projects in July to expand the FM 1960 East corridor from four to six lanes and add a raised median. Phase 1 includes the road between Business FM 1960 to east of Twigsworth Lane. Phase 2 will expand the road from Twigsworth Lane to just west of the Lake Houston bridge. Phase 2 will also add a bridge over the West Lake Houston Parkway intersection. Construction on the phases will begin in mid- to late 2020.
Timeline: mid- to late 2020-2023 (Phase 1) and mid- to late 2020-2024 (Phase 2)
Cost: $64 million (Phase 1), $70 million (Phase 2)
Funding sources: federal funding, TxDOT