Type of work: new construction
Timeline: May 1-Nov. 30
Estimated cost: $500,000
2. Scholars and Scoundrels Boardwalk: 25140 Kingsland Blvd., Ste. 1000, Katy
Type of work: new construction
Timeline: April 11-July 11
Estimated cost: $325,000
3. Johnny Ritas: 27120 Fulshear Bend Drive, Ste. 100, Fulshear
Type of work: renovation/alteration
Timeline: May 5-July 31
Estimated cost: $250,000
4. Ivy Kids Ealry Learning Center Elyson: 23101 Beckendorf Road, Katy
Type of work: new construction
Timeline: Sept. 1, 2022-Sept. 30, 2024
Estimated cost: $2.5 million
5. Sidewalks along Westheimer Parkway: 25600 Westheimer Parkway, Katy
Type of work: new construction
Timeline: March 14-April 14
Estimated cost: $55,000