On Oct. 6, the Cy-Fair ISD board of trustees approved the construction proposal for a $6.1 million renovation project at Bridgeland High School, funded by a 2019 bond, officials said.
What we know
According to district documents, the scope of work for the renovation includes:
- New orchestra rehearsal hall and practice rooms
- Two new art classrooms
- A recoating of the track surface
- An outdoor athletics storage building
- Safety and security upgrades across the campus
All CFISD campuses were impacted by the $1.7 billion bond approved in 2019, CFISD Chief Operating Officer Matt Morgan told Community Impact on Oct. 16. Many of them received similar security enhancements, fine arts additions and improvements to athletic facilities, he said.