Ongoing projects
1. Hwy. 105 widening
Project: From 10th Street to South Loop 336, Hwy. 105 is being reconstructed and widened from two to four lanes.
Update: This project is 32% completed, according to a Sept. 16 media update from the Texas Department of Transportation.
- Timeline: March 2023-third quarter 2027
- Cost: $52.35 million
- Funding source: state funds
Project: I-45 is undergoing a northbound ramp reversal between FM 830 and FM 1097 in Willis.
Update: According to a Sept. 16 media update from TxDOT, this project is 40% complete.
- Timeline: February 2024-second quarter 2025
- Cost: $3.17 million
- Funding source: state funds
Project: Hwy. 105 is being widened and reconstructed from two to four lanes between South Loop 336 to FM 1484.
Update: This project is 73% complete, according to a Sept. 16 media update from TxDOT.
- Timeline: October 2022-third quarter 2027
- Cost: $89.88 million
- Funding source: federal, state funds
Project: TxDOT is using an existing right of way on Hwy. 242 between FM 1488 and I-45 to widen lanes and restripe the intersections.
Update: According to a Sept. 16 media update from TxDOT, this project is 34% complete.
- Timeline: October 2023-first quarter 2026
- Cost: $29.11 million
- Funding source: federal, state funds
5. Eastbound flyover construction on Hwy. 242
Project: Montgomery County commissioners and TxDOT are funding the construction of a flyover from northbound I-45 to eastbound Hwy. 242.
Update: As of the most recent update available Oct. 2, the TxDOT project tracker listed the project as ready to bid on Sept. 1 and $268,054 had been spent on project engineering and construction.
- Timeline: late 2024-TBD
- Cost: $19.1 million
- Funding source: Montgomery County, federal funds