Timeline: October 2021-first quarter 2024
Cost: $9.83 million
Funding sources: TxDOT, federal
2. A TxDOT project is underway to reconstruct and widen a portion of Hwy. 105 east of Conroe. The project, taking place between South Loop 336 and FM 1484, will widen the road from two to four lanes. It was 13% completed as of a June 6 update from TxDOT.
Timeline: February 2023-third quarter 2026
Cost: $88.92 million
Funding source: TxDOT
3. The widening project on FM 1097 between Lake Conroe Hills Drive and Blueberry Hills Road was 22% completed as of a June 6 update from TxDOT. The project widens FM 1097 in Willis from two to four lanes with a continuous left turn lane. Another $14.86 million widening project on FM 1097 between Anderson Road and Lake Conroe Hills Drive is 99% complete.
Timeline: second quarter 2022-first quarter 2024
Cost: $16.1 million
Funding sources: TxDOT, federal
4. TxDOT crews are working on an overlay project on FM 2854 between Hwy. 105 and the San Jacinto River. The project, which was 23% completed as of a June 6 update, includes repairing the road surface and adding turn lanes at Hwy. 105 and Collier Cemetery, Deer Lake Lodge and Ponderosa roads.
Timeline: January 2023-first quarter 2024
Cost: $10.41 million
Funding source: TxDOT