The city of Conroe is building a four-lane roadway extension from Pollok Drive to Farrell Road, which includes the bridge over Crystal Creek.
Cost: $12.5 million
Timeline: April 2020-April 2021
Funding source: city of Conroe
2. New traffic signal
The city of Conroe is adding a traffic signal at North Loop 336 and Montgomery Park Boulevard.
Cost: $245,684
Timeline: Oct. 22, 2020-April 2021
Funding source: city of Conroe
3. Hwy. 105 widening
A project by the Texas Department of Transportation widening Hwy. 105 from 10th Street to South Loop 336 is slated for bids in June 2022.
Cost: $38 million
Timeline: June 2022-TBD
Funding source: TxDOT