Several road projects are set to begin construction soon, are currently under construction or have recently been completed across League City. Here are several updates to projects the city is working on.

The details

League City City Council unanimously approved the following project updates at its Aug. 26 meeting:

FM 518 at Country Lane intersection Improvements
  • Scope: Full intersection rebuild at FM 518 and Country Lane, including signal upgrades, mast arm installation and safety enhancements
  • Contractor: Statewide Traffic Signal Company
  • Cost: $458,457 construction contract
  • Timeline: The contractor must begin within 10 days of receiving notice to proceed, with a completion period of 320 days.
  • Why it matters: This is the first phase of a larger traffic signal reconstruction program designed to modernize older intersections throughout League City.
UPS battery backups at intersections
  • Scope: The purchase and installation of 13 uninterruptible power supply battery backup systems with remote monitoring at major intersections across League City
  • Vendor: Paradigm Traffic Systems, Inc.
  • Cost: $92,430
  • Why it matters: Battery backups keep traffic lights operational during power outages, improving safety and reducing post-storm recovery time.
Internally illuminated street name signs
  • Scope: The purchase of 24 internally illuminated street name signs through a BuyBoard cooperative contract
  • Vendor: Paradigm Traffic Systems, Inc.
  • Cost: $98,200
  • Why it matters: The signs improve nighttime visibility and help drivers navigate more safely.