Despite major delays and challenges, an “aggressive” approach to construction means the widening of Hwy. 146 will likely finish over a year ahead of schedule, an official working on the project said.
Will Bradley—senior project manager with Webber LLC, the construction contractor—said he expects the $201 million Hwy. 146 project to finish in May 2023—a year ahead of the June 2024 deadline. As of late November, work was 45% done, but Webber had used only 34% of its allotted time to complete the project.
“We wanna be ahead on work and not using all the time [allotted to us],” Bradley said. “This means we’re ahead of schedule.”
When complete, the existing Hwy. 146 bridge over Clear Lake will have three lanes in each direction between Red Bluff Road and Hwy. 96.