See what’s happening with ongoing or upcoming road projects around Dallas-Fort Worth.
Collin County
1. Meadow Hill Drive
Project: Construction will include repairing asphalt paving with reinforced concrete along Meadow Hill Drive from just west of North County Road. The project will also include building two single-lane roundabouts and making several drainage and driveway improvements, according to Frisco city documents.
Update: At a May 5 meeting, Frisco City Council approved a contract with McMahon Contracting LP for construction.
- Timeline: June 2026-fall 2027
- Cost: $2.16 million
- Funding source: city of Frisco
2. Coit RoadProject:
Coit Road in Prosper will transition into six lanes. Currently, construction crews are working to expand the road to four lanes and prepare infrastructure, including utilities and sidewalks, for future expansion.
Update: Phase 2 has been delayed and will start at the end of the year. Phase 1 of the project, which covers Coit Road from First Street to Prosper Trail, is on track to wrap up this fall.
- Timeline: Phase 2 to start at the end of the year
- Cost: $24 million
- Funding source: town of Prosper, Collin County
3. Intersection improvements at Tennyson Parkway and Corporate DriveProject:
Workers are adding new turn lanes, signal upgrades and safety improvements to the intersection at Tennyson Parkway and Corporate Drive in
Plano. This intersection will receive two left-turn lanes.
Update: The westbound through-lane and eastbound turn lane will be closed 24/7. Public Works Community Investment Program Manager Drew Zaeske said construction is expected to be completed by the third quarter of 2026.
- Timeline: October 2025-June 2026
- Cost: $8.1 million
- Funding source: city of Plano
4. Tarrant CountyFM 1938 median project
Project: The work on FM 1938 in Keller will include converting the two-way left-turn lane into a 14-foot-wide raised median. At intersections with median breaks, the median will be reduced to a width of 2 feet, and a 12-foot-wide left-turn lane will be created. The project will be from Southlake Boulevard to Emerald Hills Way, and the lane configuration will not change. Additionally, the road from FM 1709 to Starnes Road will be reconstructed.
Update: Keller drivers will encounter moving interior lane closures as progress continues south toward North Richland Hills. Work in Keller is expected to finish in June.
- Timeline: March 2026-summer 2027
- Cost: $9.9 million
- Funding source: Texas Department of Transportation
5. Ray White Road widening improvementsProject: Ray White Road in Fort Worth will be widened to a four-lane divided road between Mirage Drive and the bridge over Bear Creek. Additional improvements include adding a sidewalk on both sides of the road, installing street lights, storm drain improvements and constructing modifications to the roundabout at Ray White Road and Park Vista Boulevard.
Update: The main lanes and roundabout modifications are now paved. The contractor is in the process of pouring sidewalks and finalizing the installation of streetlights and the traffic signal at Wall Price.
- Timeline: expected to finish in late summer, early fall
- Cost: $22 million
- Funding source: city of Fort Worth