Upcoming
1. Coit Road updates
Project: The project will design and construct four lanes of an ultimate six-lane concrete divided roadway from First Street to Prosper Trail. This is phase one of the larger Coit Road reconstruction project. Phase two will look at Prosper Trail to Frontier Parkway.
Update: The project is in the preconstruction phase and will start construction later this summer.
- Timeline: August 2025-January 2027
- Cost: $23.64 million
- Funding source: town of Prosper
Project: First Street from Dallas North Tollway to Coleman Street will be expanded from a two-lane rural roadway to a four-lane divided roadway.
Update: The project is in the design phase with a target construction start date for later this fall.
- Timeline: fall 2025-summer 2027
- Cost: $21.79 million
- Funding source: town of Prosper
Project: Teel Parkway will be a four-lane divided roadway from north First Street to Freeman Way, once complete.
Update: The project is currently in the design phase, which is 68% complete.
- Timeline: winter 2026-summer 2027
- Cost: $800,000
- Funding source: town of Prosper
Project: The project will reconstruct Pecan Street from Arizona Drive to Florida Drive. It will also include replacements of pavement on Arizona Drive from Pecan Street to Beech Street and Illinois Street from Walnut Street to Beech Street.
Update: The project is in the design phase and is on track. An estimated completion date has not yet been determined.
- Timeline: TBD
- Cost: $3.2 million
- Funding source: city of Celina
5. First Street construction
Project: The project will create a four-lane concrete roadway with a median from Stuber Elementary School to North Dallas Parkway
Update: All paving activities have been completed, according to the town of Prosper’s website. Crews are clearing the roadway in preparation for striping operations, which were expected to begin the week of July 14.
- Timeline: spring 2023-fall 2025
- Cost: $30.89 million
- Funding source: town of Prosper
Project: Sunset Boulevard from Preston Road to Coit Road will be repaved with asphalt.
Update: The project is under construction.
- Timeline: late 2024-February 2026
- Cost: $4.2 million
- Funding source: city of Celina
Project: This project will fund the design and reconstruction of Arizona Drive from Pecan Street to Walnut Street.
Update: The road is partially closed, making it ready for new construction. The project is on track, according to the city’s website.
- Timeline: estimated October 2025 completion
- Cost: $830,000
- Funding source: city of Celina