Traffic has been shifted to the new concrete pavement, according to an April 8 update on the town’s capital improvement website. Crews are currently working on grading and placing fill for Legacy Drive and the westbound lanes of First Street.
The details
Construction is about 72% complete, according to the town’s capital improvement website.
First Street from Stuber Elementary School to Dallas Parkway will be expanded to a four-lane divided roadway.
Construction started in 2023 on the estimated $30.89 million project, with it projected to wrap in the fall of this year.