Crews in Plano were expected to move to Alma Road's northbound lanes in late July after completing the southbound lanes between Parker Road and Park Boulevard.

The project, which began in May, is part of a series of pavement repairs along the major Plano thoroughfare.

One lane will be closed at all times during the project, with an additional lane closed on weekdays during the day.

Timeline: May-August

Cost: $800,000


Funding source: city of Plano