Construction is ongoing for the three remaining buildings of the Park West Crossing master-planned business park in Coppell, said Matthew Smith, vice president of ML Realty Partners, the project developer.

The project began in February 2023 at an estimated cost of $18.2 million, according to a project registration with the Texas Department of Licensing and Regulation. Construction is scheduled to be complete in the second quarter of 2024, Smith said. The three new buildings will be warehouse and office spaces.

The buildings are each along Southwestern Boulevard at varying square footage, he said.
  • 125 Southwestern Blvd.: 24,620 square feet
  • 221 Southwestern Blvd.: 95,071 square feet
  • 301 Southwestern Blvd.: 109,744 square feet
With the completion of the new buildings, the business park will contain a total of 11 buildings ranging from 24,600-142,500 square feet, Smith said.