Construction started in late 2023 to make drainage upgrades and add a new sidewalk along Pate Orr Road South in Keller.

The details

When complete, the project will have added a pedestrian connection with 4-foot sidewalks between Phillips Drive and Brookstone Court. While construction is ongoing, however, Pate Orr’s southbound lane from Brookstone to Bear Creek Parkway will close for about four months. Southbound Pate Orr will be open to local traffic only to Brookstone Court.

The $646,000 project is scheduled to be completed in April.