Jackson Road Bridge in Colleyville is now expected to open in the summer, according to the Texas Department of Transportation.

The details

Due to a utility conflict with the water line, the project was paused in March, then resolved in late May, TxDOT Public Information Officer Val Lopez said.

Construction restarted in July and Lopez said there was a redesign of an additional bridge column was also put in place, further delaying the opening date.

The $1.75 million project started in January 2024. TxDOT originally planned for construction to be completed by the end of 2024, then the completion date was extended to early 2025.


The project

The construction intends to widen the travel lanes to 12 feet, providing the addition of four-foot-wide shoulders and five-foot-wide sidewalks on both sides of the bridge, Community Impact previously reported.