Work to replace the bridge on North White Chapel Boulevard in Southlake is making progress.

In March, crews worked to install stronger infrastructure on the east half of the project. On the west half, crews made progress on utility relocation. Contractors are also completing grading for the roadway leading up to the bridge and enhancing drainage.

What you need to know

When the project is complete, the revelation of the road and the bridge will be raised, and a pedestrian pathway will be added to the west side. The $6.9 million project is slated for a late 2024 completion date.