Pending inclement weather, NorthGate Constructors will partially remove a portion of the SH 360 bridge over Stone Myers Parkway in Grapevine as part of the SH 121/360 interchange project. Removing a portion of this bridge will allow crews to begin building a new ramp over Stone Myers. To complete the work, two weekend closures will be required:
Full Highway Closure: Northbound SH 360 at Stone Myers
Dates and times: From 8 p.m. on Friday, Oct. 7, until 6 a.m. on Monday, Oct. 10.
Detour: Traffic will be detoured to the northbound SH 360 frontage road. Click
here to see a detour map.
Full Road Closure: East and westbound Stone Myers under SH 360
Dates and times: 8 p.m. on Friday, Oct. 7, until 6 a.m. on Monday, Oct. 10.
Detour: Eastbound Stone Myers traffic will be detoured to Euless-Grapevine Road. Westbound Stone Myers will be detoured to Mustang Drive Click
here to see a detour map.
The $61 million SH 121/360 Interchange project will add new direct connectors for SH 114, SH 121 and SH 360 that will minimize weaving, reduce congestion and improve safety in the area. The improvements were included in the original $1.6 billion DFW Connector project, but funds were not available at that time to complete the entire project. When congestion funding became available for these improvements in February 2016, the Texas Department of Transportation and NorthGate Constructors negotiated a plan to rebuild this portion of the original project.