TxDOT: Completion of SH 26 construction in Colleyville delayed to 2020

Construction along SH 26 in Colleyville causes delays to traffic.

Construction along SH 26 in Colleyville causes delays to traffic.

Construction of the SH 26 widening project will continue into 2020, officials said at the July 2 Colleyville City Council meeting.

The $38.2 million widening project stretches along SH 26, which is the main business corridor for the city of Colleyville. The area has experienced "unusual weather events" that have impacted the schedule, said Minh Tran, a Texas Department of Transportation area engineer, to the Colleyville City Council at its latest meeting. The main reason for the construction delays, however, is due to utility conflicts.

"All of that combined pushed out the schedule," he said. "We’ll continue working with the contractor to do what we can."

The new timeline Tran presented pointed to Phase 3 of the project being finished by the end of the year. After Phase 3 is finished, Phase 4 will begin and is expected to take five more months to complete.

This changes the original timeline that was presented to council, which had Phase 3 slated to finish in June and Phase 4 to finish by the end of the year.

City Council members expressed their disappointment with the news.

"I'm concerned about the schedule," Mayor Richard Newton told Tran.

He pointed out the city is planning to install landscaping and do some beautification work along SH 26. While the city is finalizing design plans and purchasing products, any delays on SH 26 will result in a delay for the city, he said.

"To be perfectly honest I don’t have a lot of confidence that we’re going to meet these schedules," Newton said. "The Glade Road utility conflict has been there for months and months. ... Your answer was we need to coordinate with the city staff. I’m concerned about that, and I would like more specific answers so our planning doesn’t get impacted from what it is today."

TxDOT set these new deadlines since the northbound lanes of SH 26 are almost done, Tran said. Once crews have finished Phase 3 and begin work on Phase 4, that work will consist mainly of median construction. It is unlikely crews will encounter utility conflicts in the middle of the road, he said.

TxDOT does need to work with Colleyville city staff to finalize decisions for the landscaping along the road so it can stay on schedule, Tran said.

Newton said city staff is more than willing to cooperate with TxDOT and stands ready to help as soon as needs are communicated.

"Please do everything possible to keep the schedule from slipping," Newton said.
By Miranda Jaimes
Miranda has been in the North Texas area since she graduated from Oklahoma Christian University in 2014. She reported and did design for a daily newspaper in Grayson County before she transitioned to a managing editor role for three weekly newspapers in Collin County. She joined Community Impact Newspaper in 2017 covering Tarrant County news, and is now back in Collin County as the editor of the McKinney edition.


MOST RECENT

Richardson Bike Mart has about 11,000 bicycles on back order. (File photo/Community Impact Newspaper)
Richardson shop has 11,000 bicycles on back order and more DFW news

Read the latest Dallas-Fort Worth business and community news.

Thirteen drive-thru grocery stores operated by the Salvation Army of North Texas are offering backpacks filled with supplies. (Courtesy Salvation Army)
Salvation Army expands North Texas grocery service locations to include school supplies, protective equipment

Backpacks filled with school supplies, personal protective equipment, financial assistance resources and U.S. Census forms will be available at the 13 existing locations.

Cottonwood Creek Trail features platforms for viewing wildlife and fishing in Cottonwood Creek. (Courtesy Visit Frisco)
Trails system in Frisco expands and more DFW-area news

Read the latest business and community news from the DFW area.

Rapid nasal swab antigen tests are recommended as options for individuals who were potentially exposed to a confirmed positive carrier, as well as for people traveling, returning to work or undergoing a medical procedure. (Courtesy Total Primary Care)
Find out where to get a 15-minute COVID-19 test in Austin, Dallas-Fort Worth metros

Rapid nasal swab antigen tests are recommended as options for individuals who were potentially exposed to a confirmed positive carrier, as well as for people traveling, returning to work or undergoing a medical procedure.

(Courtesy Adobe Stock)
State Farm office opens in Grapevine

A new State Farm insurance office opened Aug. 1 at 414 N. Main St., Ste. 106, Grapevine.

(Ellen Jackson/Community Impact Newspaper)
Changes in Colleyville stormwater fee structure could fund flood mitigation

Flooding events at dozens of road crossings in Colleyville have led city officials to compile a laundry list of stormwater projects to take on in the decades to come.

A mother and daughter visit at Seasons Assisted Living & Memory Care in Conroe earlier in the pandemic. (Courtesy Seasons Assisted Living & Memory Care)
Texas allows limited visitations to nursing homes, long-term care facilities

Facilities that meet the requirements will allow limited visitations, but you still will not be able to hug or kiss your loved one.

(Courtesy Fotolia)
Brumlow Avenue lane closures in Southlake make way for waterline extension

Crews began work July 20 on a waterline extension project on the 1700 block of Brumlow Avenue.

SweetStop bakery holds grand opening in Richardson and more DFW-area news

Read the latest business and community news from the Dallas-Fort Worth area.

The Confederate Soldiers Monument stands on the south grounds of the Texas Capitol. A group of Democratic lawmakers have called for its removal, along with other statues and portraits honoring the Confederacy. (Jack Flagler/Community Impact Newspaper)
State legislators seek removal of Confederate monuments at Texas Capitol

The decision may ultimately lie with Gov. Greg Abbott and the rest of the State Preservation Board, which last year authorized the removal of a plaque in the Capitol that said slavery was not an underlying cause of the Confederate rebellion.