More than $24,000 released to GCISD as high school construction contracts close

0

Following a change order to close a construction contract, $24,298 will be released from the contract and returned to Grapevine-Colleyville ISD.

Lee Lewis Construction has completed the mechanical renovations at Colleyville Heritage High School and Grapevine High School, per its 2016 bond program. Owner contingency funds, unspent contractor contingency funds in the contract and the unspent amount of an allowance for a roof repair at Colleyville Heritage High totaled $24,298, which will be returned to the district. This money will be placed in the 2016 bond program until all bond projects are complete.

The GCISD board of trustees unanimously approved the change order April 29. Trustee Doug Noell noted that is about a 3% savings on what the board had approved in the budget for the project.

With the approval, the construction contract has closed, and the work identified in the bond program for these two campuses is substantially complete.

While this particular contract has closed, work continues at Grapevine High for upcoming renovations.

Share this story
COMMENT

Leave A Reply

Miranda Jaimes
Miranda has been in the North Texas area since she graduated from Oklahoma Christian University in 2014. She reported and did design for a daily newspaper in Grayson County before she transitioned to a managing editor role for three weekly newspapers in Collin County. Now she's in Tarrant County, mostly, and has been an Impacter since 2017 as the editor of the Grapevine/Colleyville/Southlake edition.