Four Frisco intersections will be seeing improvements such as turn lanes and traffic signals over the next few months.

Frisco City Council members Jan. 7 approved a $1.85 million construction contract for four new traffic signals and two new left turn lanes at four intersections.
  • Eldorado Parkway and Research Road
  • West Stonebrook Parkway and Witt Road
  • Stonebrook Parkway at FM 423 Walmart
  • Lebanon Road at 4th Army Road


The two left-turn lanes will go to the Eldorado Parkway and Research Road intersection.



The details


Included in the $1.85 million cost is a $150,000 contingency fee, which will be used during construction to address field changes or adjustments to quantities.

Construction began in January and should finish in phases—the construction contract specifies all of traffic signal work at Eldorado Parkway and Research Road must be completed within 60 days and the signal work at Stonebrook Parkway and Witt Road must be completed within 90 days.

All other signal and intersection work must be completed within 180 days, according to meeting documents.