Check out these seven transportation projects in Frisco.

Upcoming projects

1. Teel Parkway widening

Project: The project will widen Teel Parkway from two lanes to four lanes from Stafford Middle School to Olive Branch Drive.

Update: The project is in the design phase and construction is expected to start later this year.
  • Timeline: mid 2025-end of 2026
  • Cost: $10 million
  • Funding source: city of Frisco
2. Legacy Drive widening


Project: The construction will widen and reconstruct the roadway from Lebanon Road to Stonebrook Parkway and Stonebrook Parkway from Legacy Drive to 4th Army Drive.

Update: The project is in the planning phase with construction expected to start next year.
  • Timeline: mid 2026-mid 2027
  • Cost: $15 million
  • Funding source: city of Frisco
3. Ohio Drive at Wade Boulevard roundabout

Project: A new roundabout will be added to the corner of Ohio Drive and Wade Boulevard.

Update: The project is currently in the planning phase.
  • Timeline: early 2026-early 2027
  • Cost: $4 million
  • Funding source: city of Frisco
Ongoing projects


4. Panther Creek Parkway construction

Project: The project runs Panther Creek Parkway from Dallas North Tollway to Preston Road. The project will create a new six-lane roadway to fill the last remaining gap of Panther Creek Parkway in Frisco.

Update: The contractor is working on improvements to the storm drain, water line and sanitary sewer line. Roughly 70% of the improvements to the storm drainage infrastructure is complete, according to a January engineering council report. Paving is anticipated to begin early this year.
  • Timeline: early 2024 - end of 2025
  • Cost: $56.4 million
  • Funding source: city of Frisco, Collin County
5. Hillcrest Road construction

Project: The roadway will create a four lane divided roadway.


Update: The project is under construction and will be completed later this year.
  • Timeline: early 2024-September 2025
  • Cost: $5.99 million
  • Funding source: city of Frisco
6. Mahard Parkway construction

Project: The project will construct a six lane roadway from PGA Parkway to US 380.

Update: The project is under construction after bidding in late 2024. The road will be part of the Firefly Park development.
  • Timeline: late 2024-mid 2026
  • Cost: $11.03 million
  • Funding source: city of Frisco
Completed projects

7. Gartner Road traffic signal installation


Project: A new traffic signal was added to the intersection of Main Street and Gartner Road.

Update: The light was activated in December, according to a January engineering council report. It will serve the existing Grove neighborhood on the south side of Main Street and the future Grove neighborhood on the north side with sales opening in early 2025.
  • Timeline: mid 2024-end of 2024
  • Cost: $250,000
  • Funding source: city of Frisco