Here are six road projects that are under construction or will soon break ground in Frisco.

Ongoing projects

1. Frisco Street construction

Project:
The project will construct a two-lane roadway from Universal Parkway to PGA Parkway.

Update: The project is in the construction phase after the design phase ended in quarter three of 2023.
  • Timeline: 2023-end of 2024
  • Cost: $20.86 million
  • Funding source: city of Frisco
2. Universal Parkway construction


Project:
The project will construct a six-lane divided roadway from Dallas Parkway to Panther Creek Parkway. The roadway is being built in anticipation of the Universal Kids Resort project.

Update: The project is under construction after the design phase ended in 2023.
  • Timeline: 2023-2024
  • Cost: $12.93 million
  • Funding source: city of Frisco
Upcoming projects

3. Stonebrook Parkway at Walmart stop light installation

Project:
Officials will add a stop light to the intersection by Walmart on Stonebrook Parkway just past FM 423.


Update: The project is in the design phase and will go out to bid for construction later this year.
  • Timeline: 2024-quarter one of 2025
  • Cost: $250,000
  • Funding source: city of Frisco
4. Stonebrook Parkway at Witt Road traffic signal installation

Project:
The project will add a new traffic signal to the intersection of Stonebrook Parkway and Witt Road.

Update: The project is in the design phase, and the project will go out to bid for construction later this year.
  • Timeline: 2024-quarter one of 2025
  • Cost: $250,000
  • Funding source: city of Frisco
5. Lebanon Road construction

Project:
The road will be widened from a four-lane divided roadway to a six-lane divided roadway from FM 423 to Todd Drive.


Update: The project is in the design phase and is projected to go out for construction bids by the end of the year.
  • Timeline: 2024-2026
  • Cost: $26.5 million
  • Funding source: city of Frisco
6. Legacy Drive widening

Project:
The project will widen and reconstruct the existing roadway from Lebanon Road to Stonebrook Parkway and Stonebrook Parkway from Legacy Drive to 4th Army Drive.

Update: The project is in the planning phase, and construction is estimated to start in 2025.
  • Timeline: late 2025-March 2027
  • Cost: $15 million
  • Funding source: city of Frisco