Here are 10 transportation projects that are expected to start, have started or recently finished in Frisco.

Upcoming

1. Main Street construction

Project: The project will span Main Street from BNSF Railway to North County Road and Fourth Street from Main Street to Elm Street. This is part of a greater downtown redevelopment project.

Update: The project is expected to start construction in April.
  • Timeline: April 2024-early summer 2026
  • Cost: $25 million
  • Funding source: city of Frisco
2. US 380 utility relocations


Project: This project is part of a greater US 380 construction project. The utilities will be moved to make room for the upcoming road widening project. The utility work will be moved from Preston Road to Dove Creek Drive and Hollyhock Road to FM 423.

Update: The utility work is in the planning phase and construction is set to start in 2025. The Collin County Commissioners voted in February to cover the costs of moving the utilities, which will later be partially reimbursed by the Texas Department of Transportation.
  • Timeline: Q3 2025-Q4 2026
  • Cost: $8 million
  • Funding source: Collin County, Texas Department of Transportation
3. Teel Parkway widening

Project: Teel Parkway will be expanded from a two-lane roadway to a four-lane roadway. The project spans from Stafford Middle School drive to Olive Branch Drive.

Update: The project is in the planning phase and construction will start in 2025.
  • Timeline: Q2 2025-Q2 2026
  • Cost: $8.5 million
  • Funding source: city of Frisco
4. Lebanon Road widening


Project: Lebanon Road will be widened from a four-lane divided roadway to a six-lane divided roadway.

Update: The project is in the design phase with construction to start later this year.
  • Timeline: Q3 2024-Q4 2025
  • Cost: $26.5 million
  • Funding source: city of Frisco
5. Legacy Drive widening

Project: Legacy Drive will be widened from Lebanon Road to Stonebrook Parkway and Stonebrook Parkwarkway from Legacy Drive to 4th Army Drive.

Update: The project is in the planning phase.
  • Timeline: Q3 2025-Q4 2026
  • Cost: $15 million
  • Funding source: city of Frisco
6. Hillcrest Road construction


Project: The project will construct a four-lane divided roadway from Panther Creek Parkway to PGA Parkway.

Update: The project is still in the design phase. The bid phase should be completed by the end of March.
  • Timeline: March 2024-March 2025
  • Cost: $5.38 million
  • Funding source: city of Frisco
Ongoing projects

7. Emergency signal installation

Project: A new emergency signal is being installed at Fire Station No. 5 on Eldorado Parkway.


Update: The project is currently under construction and nearing completion.
  • Timeline: Q4 2023-June 2024
  • Cost: $333,333
  • Funding source: city of Frisco
8. Coit Road traffic light

Project: A new traffic light is being added to the Coit Road and Caprock Drive intersection.

Update: The project started construction in 2023 and will be completed in several months.
  • Timeline: Q4 2023-June 2024
  • Cost: $250,000
  • Funding source: city of Frisco
9. Stonebrook pedestrian signals

Project: A new pedestrian hybrid beacon signal is being added to the Babbling Brook Drive and Stonebrook Parkway intersection.


Update: The project started early this year and will be completed in the next few months.
  • Timeline: January-June 2024
  • Cost: $200,000
  • Funding source: city of Frisco
Completed

10. Elm Street construction

Project: Elm Street was reconstructed with parking and pedestrian paths added. This is part of a greater downtown redevelopment project.

Update: The project has been completed
  • Timeline: July 2023-February 2024
  • Cost: $5.1 million
  • Funding source: city of Frisco