Check out some of Frisco’s in-the-works roads projects.

Lebanon Road widening

The project: This project will turn Lebanon Road into a six-lane roadway from FM 423 to Todd Drive, according to the city’s capital improvement projects database. As-is, Lebanon is a four-lane divided road.

The update: Designs for the road should be finalized sometime this summer. Current projections have construction finished just before 2026, according to the city’s project database.
  • Timeline: late 2024-late 2025
  • Cost: $26.5 million
  • Funding source: city of Frisco
Legacy Drive construction

The project: The project was to create a six-lane divided roadway between Panther Creek Parkway and PGA Parkway as a connection to US 380, according to the city's projects database.


The update: This road is officially open to drivers as of Feb. 14.
  • Timeline: late 2022-early 2024
  • Cost: $62 million
  • Funding source: city of Frisco
Ohio Drive and Gaylord Parkway roundabout

The project: The intersection at Gaylord Parkway and Ohio Drive will be converted into a multilane roundabout starting sometime late this year, according to the city’s project database.

The update: Designs should wrap up sometime this summer, according to the city’s project database.
  • Timeline: late 2024-late 2025
  • Cost: $3.9 million
  • Funding source: city of Frisco
Panther Creek Parkway construction

The project: The Panther Creek Parkway project includes constructing a six-lane divided roadway between the Dallas North Tollway and Preston Road.


The update: Designs are slated to wrap up before the end of March with construction beginning shortly after. Once work begins, it should finish before the end of 2025.
  • Timeline: early 2024-late 2025
  • Cost: $55 million
  • Funding source: Collin County and the city of Frisco
Fields Parkway construction

The project: This project, the second phase of a longer reconstruction project, will bring a four-lane road to connect FM 423 and Fields Parkway, according to Frisco’s project database.

The update: Construction on the project is still ongoing and expected to finish in mid-2024.
  • Timeline: late 2022-mid-2024
  • Cost: $14.12 million
  • Funding source: city of Frisco
North Frisco Street construction

The project: This project will bring a two-lane roadway to a stretch of land between the incoming Universal Parkway and PGA Parkway.


The update: Construction should finish before the end of the year, according to the city’s project database.
  • Timeline: late 2023-late 2024
  • Cost: $20.86 million
  • Funding source: city of Frisco
Universal Parkway construction

The project: This will bring a new six-lane divided roadway to connect Dallas Parkway with Panther Creek Parkway, according to Frisco’s project database.

The update: The name for the road was announced in early December with an update on the overall Universal Kids Resort project. It should finish in late 2024, a little under two years before the park is expected to open.
  • Timeline: late 2023-late 2024
  • Cost: $12.94 million
  • Funding source: city of Frisco
Teel Parkway widening

The project: Plans are underway to widen Teel Parkway from two to four lanes between an unnamed road at Stafford Middle School and Olive Branch Drive.


The update: This project is still in its planning phase with designs expected to be finalized by mid-2025. Construction should begin shortly after and last around one year.
  • Timeline: mid-2025-mid-2026
  • Cost: $8.5 million
  • Funding source: city of Frisco