Donnie Mayfield Way extension
Donnie Mayfield Way will be extended from PGA Parkway to the PGA elevated storage tank.
The project will extend the two-lane roadway including 30 feet of water lines, according to a Frisco capital improvement report.
The project is in the design phase, and construction is slated to start in fiscal year Quarter 2 from April-June. The design is about 95% complete.
- Timeline: June 2023-March 2024
- Cost: $1.99 million
- Funding source: city of Frisco
Hillcrest Road construction is slated to begin no later than June.
The project will construct a four-lane divided roadway from Panther Creek Parkway to PGA Parkway, according to a Frisco capital improvement report.
The project is currently in the design phase and is 99% complete.
- Timeline: June 2023-June 2024
- Cost: $5.38 million
- Funding source: city of Frisco
Lebanon Road will be widened from a four-lane divided highway to six lanes.
The project will be done from FM423 to Todd Drive, according to a Frisco capital Improvement report.
The project is currently in the design phase and is 40% complete. Construction is anticipated to start no later than June.
- Timeline: June 2023-September 2024
- Cost: $14 million
- Funding source: city of Frisco