A portion of the Main Street widening project is ahead of schedule.
The section between Kentland Drive and Teel Parkway currently has both eastbound and westbound traffic sharing the southern half of the road. But westbound traffic is expected to move back to the northern half of the road by April 6, which is about 30 days ahead of schedule, Frisco Engineering Director Paul Knippel said during the April 2 Frisco City Council meeting.
Main is being widened to six lanes between FM 423 and Dallas Parkway. The project has been under construction since October 2017.
The project, which is projected to be complete in June, includes installing water lines and underground power lines.