Want to be first to know about the latest businesses, attractions and developments in Frisco? The following projects have been filed in the last two weeks through the Texas Department of Licensing and Regulation. The following information may be subject to change.

Bethesda Gardens Frisco: 10588 Legacy Drive, Frisco

Type of work: additions to existing building

Timeline: June 1, 2022-Jan. 1, 2024

Estimated cost: $10 million


Poached Brunch: 1612 FM 423, Ste. 300, Frisco

Type of work: renovation/alteration

Timeline: June 30-Sept. 30

Estimated cost: $300,000


Lululemon: 2601 Preston Road, Space 1079, Frisco

Type of work: renovation/alteration

Timeline: July 18-Oct. 4

Estimated cost: $650,000


Chipotle: 8847 Coit Road, Frisco

Type of work: new construction

Timeline: Sept. 19-Dec. 5

Estimated cost: $553,274


Pet Supplies Plus: 16803 Coit Road, Frisco

Type of work: new construction

Timeline: June 1-Dec. 30

Estimated cost: $600,000