The Shops at Willow Bay Lot 9: Eldorado Parkway and Glacier Drive, Block A, Lot 9, Frisco
Type of work: new construction
Timeline: Feb. 1-Oct. 31
Estimated cost: $3 million
Portoventura Coastal Cuisine: 4606 Frisco Green Ave., Frisco
Type of work: renovation/alteration
Timeline: Jan. 18-May 31
Estimated cost: $700,000
Curry Pizza House Independence: 5353 Independence Parkway, Ste. 105, Frisco
Type of work: renovation/alteration
Timeline: Feb. 1-Oct. 1
Estimated cost: $250,000
Snooze A.M. Eatery: 9169 Dallas Parkway, Ste. 120, Frisco
Type of work: renovation/alteration
Timeline: March 14-June 30
Estimated cost: $700,000
Parker University Clinic: 3800 Gaylord Parkway, Ste. 795, Frisco
Type of work: renovation/alteration
Timeline: Jan. 31-May 31
Estimated cost: $2 million