Bluebonnet Trail in Flower Mound is set for repairs after a contract was approved by town officials. Town Council members unanimously approved an over $118,888 contract for repairs to 3,250 linear feet of the trail at their meeting Dec. 16.
The details
The work will be done by Apex Concrete Construction Inc. and will consist of removing and replacing about 1,000 square yards of existing 8-foot-wide trail and associated grading and backfill, according to town documents.
Melissa Demmitt, the town’s director of communications, said the work is expected to begin in early to-mid January and last about 2-4 weeks.